B.C. Hydro extends Site C contract deadline

The fourth such deadline is March 20, 2015 after Hydro had previously called for bids by December 10, 2014, January 5, 2015 and February 20, 2015.

Even though a group of First Nations and the Peace Valley Landowners Association have filed lawsuits against the project, Hydro is moving forward with the construction process.

It is seeking proposals to prepare the north bank site, and the work is to include excavation and disposal of about 3 million cubic meters and building about 7.25 kilometers of access roads.

 