Canadian LNG project in Oregon faces one year delay for regulatory approvals 

Must Read

Crews still battling fire from crude oil train derailment in central Saskatchewan

LANIGAN, Sask. — Saskatchewan's public safety agency says crews are working in frigid temperatures as they continue to battle a fire...

Fort St John Huskies home this Thursday as they host Sexsmith Vipers

FORT ST. JOHN, B.C. - The Fort St. John Huskies will be home this Thursday, December 12,...

New study considers use of piece rates in BC’s agricultural sector

VICTORIA, B.C. - The Province has released a study on the economic impact of piece rates in...

CALGARY, A.B. – A Calgary company proposing to build a US$10-billion LNG export facility in Oregon says the project timeline is being delayed by about a year.

Pembina Pipeline Corp. says it has decided to minimize project spending at about $50 million this year as it tries to vault remaining regulatory and permitting hurdles for the Jordan Cove liquefied natural gas project at Coos Bay, Ore., and a related 370-kilometre pipeline.

The reduced level of work is expected to result in construction delays such that first gas exports are now expected one year later than the targeted date in 2024.

- Advertisement -

Pembina, which inherited the project when it purchased Veresen Inc. in 2017, said it received a draft environmental impact statement from the U.S. Federal Energy Regulatory Commission in March that provided a framework for approval of the Jordan Cove project as proposed with “reasonable” conditions.

However, a final FERC decision is not expected until next January and critical Oregon state permits aren’t expected until near the end of this year.

A previous smaller version of the project was denied by FERC in 2016 due to landowner objections and what it said was a failure to demonstrate demand for its product.

Pembina says it still intends to bring in partners for the pipeline and liquefaction facility to reduce its ownership to between 40 and 60 percent.

It said it has non-binding off-take agreements with customers in excess of the planned design capacity of 7.5 million tonnes per year but will pause executing binding deals until early 2020.

More Articles Like This