Bids submitted for the replacement of Halfway River bridge

Must Read

New cases of COVID-19 reported for both City and County of Grande Prairie

GRANDE PRAIRIE, A.B. - Alberta Health Services is reporting, as of Wednesday, two additional cases of COVID-19 for both...

Bear sighted within Fort St John near Toboggan Hill park

FORT ST. JOHN, B.C. - The City of Fort St. John is advising residents of bear sightings within the...

85 new COVID-19 confirmed across BC, four more in Northern Health Region

VICTORIA, B.C. – 85 new cases of COVID-19 were confirmed across the province, bringing the total to 4,196, as...

FORT ST. JOHN, B.C. – Bids have been submitted for the replacement of the Halfway River bridge.

As part of B.C. Hydro’s project to realign Highway 29 for the Site C reservoir, four bridges will need to be replaced, with the Halfway River bridge as a top priority.

The cost to build a new 1,042-metre bridge is estimated to be between $104 million to $134 million.

- Advertisement -

Community Interviews with Moose FM


Bids for the bridge replacement were submitted by seven contractors and joint ventures from British Columbia and Alberta.

The Ministry of Transportation and Infrastructure is now in the process of reviewing those bids.

B.C. Hydro says work is being done to prepare for the filling of the Site C reservoir, which will widen the Peace River and cover parts of the existing highway.

The filling of the reservoir is scheduled to take place sometime in early 2023.

More information on the Highway 29 realignment project can be found on the Site C Project’s website.

Here is a list of bids from contractors and joint ventures for the replacement of the Halfway River bridge:

  • PCL Constructors Westcoast Inc. (Richmond) – $134,275,613.00
  • Ledcor CMI Ltd. (Edmonton) – $131,281,266.89
  • Gateway Infrastructure Group (New Westminster) – $128,036,625.26
  • Flatiron-Aecon JV (Richmond) – $122,438,374.15
  • Surespan Construction (North Vancouver) – $117,774,865.07
  • Pennecon Heavy Civil Ltd & Jim Dent Const. Ltd JV (Nisku, Alberta) – $114,899,000
  • Eiffage-Infracon Halfway River JV (Nisku, Alberta) – $104,569,326.00